On November 3, 2026, Drax, Brookfield, and Radiant announced a partnership to develop, deliver, and operate gigawatt-scale data centre capacity at Drax Power Station in North Yorkshire. Radiant is Brookfield's UK-headquartered AI infrastructure platform. The Brookfield-Qai AI infrastructure joint venture will provide backing. Brookfield estimates that total investment in the full development could potentially exceed £20 billion, including an initial £2.5 billion for the first phase.
The plan is phased, and the language in the announcement is careful about what is a target. Phase 1 targets up to 100 MW, operational from the first quarter of 2028. Phase 2 is an ambition to ramp to 500 MW between 2028 and 2031. Phase 3 is an ambition to develop additional capacity after 2031. Progression of the first phase depends on planning, on regulatory and network approvals from the government and the system operator, and on securing a suitable tenant. A community consultation is due to begin shortly, with the formal planning process after that.
The power station is the asset
The site attributes are why the partners are there. The power station estate comprises 1,000 acres and 4 GW of grid access, with 2.6 GW of active dispatchable generation and cooling systems. The announcement also cites proximity to the UK fibre network. Drax Group chief executive Will Gardiner said the station is one of the few UK sites that can provide large-scale reliable power directly to data centre customers by utilising existing and underutilised generation capacity. He also said that if the project is constructed in full, it could become one of the largest data centres in the UK.
Radiant's role is the compute layer. Radiant chief executive Mahdi Yahya said the company is expanding its UK AI compute footprint with Drax so British researchers, startups, and enterprises can get frontier compute at home. Brookfield's head of AI infrastructure, Sikander Rashid, said the firm's capital and operating capabilities would help accelerate construction, with Radiant delivering the project. Qai chairman Abdulla Al-Misnad described the project as a major initiative under the Brookfield-Qai joint venture and part of Qai's international AI infrastructure strategy.
The partners say they welcome the UK government's new Data Centre Covenant and its pathway to accelerate time to power and planning for strategically important data centres. Their initial assessment is that the project aligns with the covenant's criteria, including energy security, local community benefits, environmental standards, reindustrialisation, and secure infrastructure. They also expect a voluntary community benefits fund, developed with communities around the station, separate from planning obligations and from Drax's existing community initiatives. Government statements in the release, including from Chief Secretary to the Treasury Emma Reynolds and science minister Chris McDonald, treat the announcement as investment interest in UK digital infrastructure. Those statements do not replace planning consent.
What it means for GPU hosting buyers
For teams buying GPU hosting, this is a power-led campus that does not yet have a named tenant for phase 1. Up to 100 MW in the first quarter of 2028 is a target, and it is conditional. The 4 GW grid access figure and the 2.6 GW of dispatchable generation describe the power station estate, not a contracted GPU hall. A buyer should ask what share of that access can be dedicated to IT load, when a network approval would actually deliver it, and whether a tenant agreement exists. Until those answers are in a contract, the partnership is a development plan.
What it means for data center developers
For developers building AI data centers, the announcement is a template that keeps showing up in this market. Pair land and an existing grid position with an infrastructure investor and a compute operator, then take the project into consultation. The speed claim depends on assets already on the estate, including generation, cooling systems, and fibre proximity. It also depends on approvals the release lists as still required. A developer copying the pattern on a site without comparable grid access should not assume the same schedule. The covenant is a policy path the companies say they fit. It is not, in this announcement, a granted connection.
The Nexus buyer guides cover how to source AI colocation and how to read a powered site before treating a headline megawatt figure as available capacity.
Nexus works on AI compute, GPU hosting, and power capacity for data center buildouts. Capacity is available by quote.