Hut 8 said on November 4, 2026 that it has fully commercialized its Beacon Point AI data center campus. The company signed a second 352 MW IT lease with the Phase 1 tenant. Hut 8 calls that contract the Phase 2 lease. In the same release, filed with the SEC, the company said construction of the campus substation has commenced, along with foundation work and underground utility work at Phase 1. Civil design for Phase 2 has started.
The lease math is in the release. The Phase 2 lease represents approximately $9.8 billion in expected base-term contract value and approximately $655.0 million of expected average annual net operating income on a triple-net, take-or-pay basis. Hut 8 says the campus now carries approximately $19.6 billion of expected base-term contract value and approximately $1.3 billion of expected average annual net operating income. Across the company's AI data center portfolio, expected aggregate base-term contract value is approximately $26.6 billion.
Signing the Phase 2 lease also moved capacity into the construction bucket. Hut 8 advanced 500 MW of utility capacity at Beacon Point into Energy Capacity Under Construction. Total Energy Capacity Under Construction is now 1,330 MW. That total is 1,000 MW at Beacon Point and 330 MW at the River Bend campus. Initial data hall delivery is targeted for the third quarter of 2027 at Beacon Point Phase 1 and the second quarter of 2028 at Phase 2. River Bend's first data hall is targeted for the second quarter of 2027. Asher Genoot, Hut 8's chief executive, said the tenant at Beacon Point is doubling its contracted capacity at the campus. He also said construction at both campuses remains on track for those delivery targets.
What the site record adds
Texas Construction Hub, reporting on November 5, adds the site record around that update. The campus is near Robstown, in Nueces County, at 4650 FM 1694. The first building is registered with the state as the Beacon Point Data Center Project. The estimated construction cost on that registration is $398,985,153 for 657,130 square feet. The owner of record is Beacon Point DC LLC, also known as Lon Hill Infrastructure LLC, of Miami. The registration lists work from September 28, 2026 to November 5, 2027. The public record number is TDLR TABS2027000611, registered on September 9, 2026. Jacobs holds the sole-source engineering, procurement, and construction management contract and is the design firm on the state registration. The same firm holds that role at River Bend.
The power figure in that report is an interconnection, not only a construction status. Texas Construction Hub says the campus has 1,000 MW of utility capacity under an interconnection agreement with AEP Texas. It also reports that an unnamed investment-grade tenant has contracted 704 MW through two 352 MW leases. That 704 MW lines up with the two 352 MW IT leases in Hut 8's release. The release does not name the tenant.
What it means for GPU hosting buyers
For teams buying GPU hosting, the useful distinction is between contracted IT load and a hall that can be energized. Beacon Point's tenant has contracted two 352 MW blocks, and 1,000 MW at the campus is now in Hut 8's under-construction total. The first data hall is still targeted for the third quarter of 2027. Substation construction, foundations, and underground utilities are the work the company says has started. A buyer who needs GPUs this year is looking at a different supply pool than this campus. A buyer planning for late 2027 should still ask which phase, which megawatts, and which utility milestone sit behind the date.
What it means for data center developers
For developers, the release is a picture of how a gigawatt campus gets capitalized before the halls are done. The Phase 2 lease is described as triple-net and take-or-pay, with expected net operating income stated alongside the contract value. Hut 8 also said it is evaluating financing structures for Beacon Point Phase 2. The physical sequence in the quarter is the one developers feel in the field. The substation starts, the foundations start, and the second phase is still in civil design.
River Bend is the comparison inside the same portfolio. Hut 8 says that campus completed structural steel and building foundations across all four data halls and initially energized its substation, with first delivery targeted a quarter earlier than Beacon Point Phase 1. Power and structure do not move on the same clock.
The Nexus buyer guides are written for teams sourcing AI colocation and reviewing site readiness before they commit to a power date. They are the right companion to a lease headline.
Nexus works on AI compute, GPU hosting, and power capacity for data center buildouts. Capacity is available by quote.