Most of October's New AI Campus Capacity Followed On-Site Power

TrendForce says three quarters of October's newly tracked AI campus capacity sits beside on-site power, while Oracle's Wisconsin halls are ahead of the grid connection.

November 7, 2026 5 min readNexus Research
Most of October's New AI Campus Capacity Followed On-Site Power

TrendForce's November 4, 2026 data center tracker says the industry's forward commitment is still growing. New capacity entering the tracker outpaced data centers that came online over the past month. Every operator's remaining build-out grew. The more useful finding is where that new capacity sat.

Three quarters of the October additions, 3,111 MW out of 4,170 MW, landed on campuses built next to their own power supply rather than waiting on the grid. Google's Tembo campus in Wyoming comes with new gas generation from Black Hills Energy. AWS's Homer City campus in Pennsylvania is being built around a 4.5 GW gas plant on a former coal station. AWS's Greek campus moves onto PPC's old lignite plant at Agios Dimitrios. TrendForce's forecast is direct. Self-supplied power will determine where and how fast the largest campuses arrive, more than tax breaks or fiber.

The tracker is not a list of megawatts already serving GPUs. TrendForce counts changes to the capacity in its system. A change qualifies only when the trigger, such as a permit, a regulatory filing, a construction contract, or an operator announcement, is dated inside the month. Capacity booked on earlier evidence is set aside. Buyers should read the 4,170 MW figure as newly recognized pipeline, not as halls that can take a rack this quarter.

AWS accounted for 911 MW of the month's additions across five campuses in four countries. The sites are Homer City in Pennsylvania, Crossroads in Virginia, Agios Dimitrios in Greece, Glendenning in New South Wales, and Obertshausen in Germany. Nearly half of that AWS total, 414 MW, sits outside the United States. The campuses range from a 20 MW first stage in Germany to 336 MW in Pennsylvania. All five are still at the permitting stage. TrendForce forecasts first capacity in 2029 to 2030.

Buildings can be enclosed before the power is approved

The sharpest example of buildings moving ahead of power is Vantage's Lighthouse campus for Oracle and OpenAI in Port Washington, Wisconsin. TrendForce describes it as a $15 billion, 1.3 GW project. Two of its four data center buildings are enclosed. The grid connection is further behind. The campus depends on more than $2 billion of new ATC transmission lines and five substations. Wisconsin regulators closed that application on September 10 after ATC filed 564 additional application documents that reflected extensive changes to the project.

Vantage had asked ATC for about 310 MW of service in 2027, with the full 1.3 GW from 2028. Oracle still guides to operation in the second half of 2027. TrendForce now forecasts 310 MW of capacity at the campus in 2027, down from 650 MW. It still carries the full 1.3 GW forecast for 2028. The constraint TrendForce names is no longer construction. It is power approval.

What it means for GPU hosting buyers

That split matters for teams buying GPU hosting. A delivery date on a campus page can describe a building, a lease, or a utility service date. Those dates are not interchangeable. At Lighthouse, shells are enclosed while the 2027 power forecast was cut. A buyer who needs a specific megawatt year should ask which number the host is selling. The October pattern also says the largest new campuses in this tracker were sited beside generation. A host that is still waiting on a multi-year interconnection is telling you a different schedule than a host standing next to a plant.

What it means for data center developers

For developers building AI data centers, the same report is a siting note. Tax incentives and fiber did not lead TrendForce's forecast for where the largest campuses arrive. Power did. The AWS additions show that a permit-stage campus can enter a tracker years before first capacity. Homer City's scale is tied to a 4.5 GW gas plant. Tembo is tied to new gas generation. Agios Dimitrios is tied to a former lignite site. Developers who control land without a credible power path are not in the part of the pipeline that grew fastest in October.

None of this creates near-term bookable GPU capacity by itself. The five new AWS campuses are forecast for first capacity in 2029 to 2030. Lighthouse's 2027 figure in the tracker is 310 MW, and that is a forecast, not a listing. Teams comparing hosts should separate energized IT load from pipeline megawatts, and they should ask who owns the generation or the interconnection request.

The Nexus buyer guides cover sourcing AI colocation and the questions that sit next to a power schedule, including site readiness and contract terms. They are a useful checklist before a capacity conversation.

Nexus works on AI compute, GPU hosting, and power capacity for data center buildouts. Capacity is available by quote.