Power for AI data center buildouts: what developers need to know

November 8, 2026

An AI data center is a power project that also holds servers. GPUs can be purchased on a commercial schedule. The utility path, the substation, and the site work often cannot.

Teams that leave power until late often find the building waiting on a study, a large piece of electrical equipment, or a line they do not control.

Interconnection is the gate

Interconnection is how a new load connects to the grid. The utility or the grid operator studies the effect of that load. The study can require upgrades on their side, on yours, or on both. The agreement that follows states how much load you may take, which upgrades are required, who pays, and which conditions you still have to meet.

Ask where the project actually is in that process. A conversation with a utility is an early step. A completed study is further along. An executed agreement is a different document from either of those. Ask the service voltage. Ask who builds the line and the substation. Ask which costs are yours. Ask whether the capacity is firm, interruptible, or still conditional on upgrades.

The names of these steps differ by region. The underlying question is the same. What has the utility approved, and what is still a request?

Also ask how the site can grow. Many AI programs take power in phases. An early block is useful when a later block has a credible path. Ask for that path in writing. The first agreement may cover only the first block.

What moves an energization date

Energization is the date the site can take useful load. A signed land contract and an issued building permit come earlier. The site can power servers only after the electrical path is ready.

The date follows the slowest chain of work. Those chains often include the utility study, transmission or distribution upgrades, large electrical equipment, on-site construction, and commissioning. High-voltage transformers and switchgear have their own lead times. Those lead times vary with the specification, the manufacturer, and whether the equipment is already on order.

A project with equipment purchased is in a different position from a project that will order after financing closes. Ask what is purchased, what has a delivery window, and what is only in the budget.

Tie any date to its conditions. A clear statement names the window and the utility schedule it depends on. A single month with no dependencies is harder to use. Utility schedules move, so the plan should say what you will do if the date moves. Some projects study a smaller first block, temporary generation, or a later phase. Each option has cost and permitting consequences of its own.

How to size the megawatts

Size the load from the IT equipment, then add the rest of the building. Start with the GPUs and the other servers. Add storage, networking, and the cooling plant. The cooling plant is electrical load. A liquid-cooled hall and an air-cooled hall do not draw the same auxiliary power. The difference varies by design.

Keep three figures separate, and ask which one a seller or a utility letter is using. A campus description can sound very large while only a smaller block can be served now. A letter can cite a requested amount that has not been studied. Use the figure that is both approved and buildable on your schedule.

  • IT load: the servers themselves.
  • Facility load: the servers plus cooling and the rest of the building.
  • Requested interconnection: the amount you ask the utility for, including later phases.

Headroom and the ramp

Leave room for a later server generation when the agreement and the site allow it. Unused headroom can still carry a cost, and some agreements expect you to ramp on a stated schedule. Match the ramp to hardware you can actually install.

Site readiness beyond the megawatts

A megawatt figure still needs land you can permit, cool, connect, and staff. Check the rest of the site before you rely on the load number.

  • Land and title. Confirm you can build the use you intend, and that the parcel fits the yards, the cooling equipment, and a later phase.
  • Zoning and permits. Data center use is allowed in some places and restricted in others. Local process, water rules, air rules, and noise rules can run on their own clock beside the utility clock.
  • Water and heat rejection. Liquid cooling and evaporative plants need a water plan. Dry cooling needs space and a design that fits the climate. Settle the mechanical concept against what the site can support.
  • Fiber. A training deployment needs robust connectivity into the building. Confirm which carriers are present, or price the time and cost of a new lateral.
  • Delivery. Confirm that servers, cooling equipment, and electrical gear can reach the pad. Road limits, crane access, and laydown space are practical limits.
  • Hazards and neighbors. Floodplain, wetlands, and incompatible neighbors are cheaper to find before you commit.
  • Operations. Decide who will staff the building, and whether that labor is available near the site. A remote location can pair a workable power path with a difficult operating plan.

What to collect before you commit

Ask for documents. Useful ones include the interconnection status and any executed agreement, a one-line diagram of the proposed electrical path, the land and zoning position, a water and cooling concept, a fiber plan, and a schedule that names its dependencies.

If a document does not exist yet, write that down as the status. A clear gap is more useful than a confident summary.

Power for a buildout and a quote for GPU hosting are different requests. Describe the one you actually have, including the load, the region, and the timing. The colocation guide and the provider checklist cover the hosting side of that conversation.

Frequently asked questions

What is interconnection?

It is the process of connecting a new load to the grid. It includes study, any required upgrades, and an agreement that states what you can take and on what conditions.

Why do energization dates move?

The date depends on studies, upgrades, equipment delivery, construction, and commissioning. A delay on any one of those chains moves the date the site can take load. How far it moves varies by project.

Which megawatt figure should I use?

Use the figure the utility has approved and that the site can build on your schedule. Keep IT load, facility load, and the amount you have requested as separate numbers.

Does a powered site include cooling and fiber?

Power is one input. Cooling, water, fiber, zoning, and physical access each need their own check. Confirm them one by one.

When is it worth talking with Nexus?

Talk with Nexus when you are sizing a buildout or looking for GPU hosting and want help judging fit. Share the load, the region, and the timeline. Power and GPU capacity are quoted against that brief.

Related reading

Describe the power, or the GPUs

Nexus works on GPU hosting and on power for data center buildouts. Tell us which one you need, and what you already know about load, region, and timing.