A proposal can look finished and still skip the items that decide whether your GPUs stay online. Use this list on the first call. Use it again before you sign.
Ask for the answers in writing. A spoken yes is difficult to rely on later. Send the list with your GPU model, the cooling those servers need, the locations you can use, and the date you want to be live.
Power and density
- How many kilowatts can you deliver to my rack, and is that number at the rack or for the room?
- Is that power reserved for me, or shared until I draw it?
- What breaker, whip, or busway do I get?
- Can that circuit change if a later server draws more?
- How is usage metered, and who owns the meter?
- What is included in the power rate, and what is billed on top, including demand charges, riders, taxes, and cooling?
- What do I pay if I use less than I reserved, and what do I pay if I need more?
- Is the rate fixed, tied to the utility, or a blend, and for how long?
Cooling
- Which designs can this room support today: air, rear-door heat exchangers, direct-to-chip liquid, immersion, or a mix?
- What cooling equipment is already installed for my deployment, and what still has to be added?
- Who owns the coolant distribution equipment, and who maintains it?
- What is the procedure if there is a leak, and who is responsible?
- Can you service cooling equipment without taking my racks offline?
Network and location
- Which carriers are already in the building, and can I bring my own fiber?
- What path do you have to the cloud region, exchange, or users I named?
- What bandwidth and latency will you describe for that specific path?
- How do my racks connect to each other, and who operates that fabric?
- Where is the building, and how long does it take a technician to arrive?
Redundancy and day to day operations
- What does the power path look like from the utility to my rack?
- Is there a second path, and what does it cover?
- Is there on-site generation, and which load does it carry?
- Is the IT load on UPS, and during which events?
- What can my team do on its own access, and what requires a ticket?
- What does remote hands include, and what does it cost?
- How do you notify me of maintenance, and how much notice is typical?
- What monitoring can I see myself, and who is on site overnight and on weekends?
Contract and commercial terms
- What is the term, how does renewal work, and how much notice do I give to leave?
- What capacity am I committing to, and how do I add or release it?
- Which fees are paid once, and which fees recur?
- What service level is written into the contract, and what credit applies if it is missed?
- What insurance do you require for my hardware?
- Can you move my equipment, and do I have to approve the move?
- What happens to my servers if I end the contract early, and what happens if you end it?
- Are there limits on the workload, the hardware vendor, or a sublease?
Timeline and what is actually ready
GPU hosting capacity is quoted. Treat a statement that space is open as an estimate until the provider confirms power, cooling, and a date for your servers.
- Which parts of this deployment exist today, and which parts still have to be built or ordered?
- What is the sequence from signature to a rack that can take my servers?
- What do you need from me, and by which date?
- What can move that date, including power work, cooling gear, fiber, and shipping?
- Is the capacity in this proposal confirmed for my hardware, or an estimate until a later check?
How to read the answers
Mark each answer as confirmed in the contract, described but not committed, or still unknown. Sign when the items your workload depends on are confirmed.
If rack density, cooling ownership, or the power charge is still unknown, keep that proposal in the open pile. Put the written answers next to the comparison points in the GPU colocation guide before you pick a winner.
Frequently asked questions
Should I send the full list at once?
Yes. Pair it with the GPU configuration, the cooling the hardware needs, the locations you can accept, and your target date. A complete brief produces a more useful reply.
What if a provider will not answer in writing?
Keep the gap visible. You may still decide to proceed. You should know which promises never entered the contract.
Do I need every redundancy feature on this list?
Match the design to the workload. A job that can pause is a different requirement from a service that has to stay up. Ask for the features you are willing to pay for, and skip the ones you are not.
Who should review the contract?
Your infrastructure lead and your counsel should both read it. If the hardware is financed, ask the lender what the facility, the insurance, and the access rules must say.
Can Nexus help compare the answers?
Yes. Send the deployment through a hosting request, or contact the team, and include the written answers you already have. Capacity is quoted to your hardware and your date.